14 & 18 Bridge Repair
The beginning of repairs on 18 bridge. Old decking was removed, and existing joists and beams were repaired as needed
The bridges originally had 3 joists or beams running under the deck. We added 2 additional joists for more strength.
New yellow pine deck boards are down and the crew is installing 6 screws per board. It took 1584 screws just for # 18